General Over View:

2014
Tony Gee & Partners for Docklands Light Railway
Beckton Depot Maintenance Shed Extension
1394
9 months to date
Equivalent of NR GRIP Stage 2 – 8
Extension of Beckton Maintenance Shed on Docklands Light Railway involving the redesign of the East End Junction. This required changes to signalling design, namely:  revised Signalling Scheme Plan; new Signalling Location Plan; new Location drawings and new bonding diagrams.

The work was carried out by the following stages: Feasibility, AIP, Detailed design, As builts and final Return of records.