  • Year:

    GRIP 3 – 4 complete (2018)

    GRIP 5 – 8 ongoing

  • Client:

    Tony Gee & Partners

  • Project Title:

    TPE Scarborough Train Servicing Facility

  • Scheme Sponsor:

    Trans Pennine Express

  • Duration:

    On Going

  • General Over View

    GRIP Stage 3-5

Background & Scope

TransPennine Express (TPE), part of First Group, were awarded a 7-year franchise in 2016 to operate services across the north of England, including routes from Manchester to Edinburgh and Glasgow. As part of their franchise obligations, TPE are introducing new rolling stock, as well as upgrading their existing fleet. To facilitate this, TPE are carrying out a number of depot upgrade across their network, as well as introducing new depot operations in a number of locations, of which Scarborough is one.

Kilborn Work & Outputs

For GRIP 3 – 4:

·         Asset condition survey and report;

·         Signalling Scheme Plan;

·         Outline Project Specification;

·         Operational Requirements Specification;

·         Risk Assessments (Trap Point; SORAT);

·         Testing Strategy;

·         IDC/IDR and multi discipline design coordination and integration.

·         Signallers’ Panel alteration; and

·         Telecoms Reference Design

For GRIP 5 – 8:

·         SSP update;

·         Location case circuitry design;

·         Signalling Design Specification;

·         Signal Sighting;

·         Telecoms Detailed Design;

·         IDC/IDR and multi discipline design coordination and integration.

·         As-Built updates; and

·         Records return